QA/QC Practices
Quality assurance is the system that prevents defects; quality control is the measurement that proves it worked. This guide collects the questions our consulting and training clients ask most about running QA/QC on Indian construction sites — how often to cast cubes on an RMC pour, what IS 456 Table 11 actually requires before concrete is accepted, when a low result becomes a non-conformity, and how trial mixes relate to an approved design mix.
The 10 most-asked questions — click any question for the answer, and the clause it rests on
A-1
What is the difference between Quality Assurance (QA) and Quality Control (QC)?
What is the difference between Quality Assurance (QA) and Quality Control (QC)?
Quality Assurance is the process side — quality plans, method statements, training, document control, internal audits. Quality Control is the verification side — cube tests, slump checks, calibration records, inspection logs. QA defines how QC is done; QC produces the evidence that QA is working. Both are needed on a concrete project and both must be documented.
Reference: IS 456:2000 Cl. 17 · ISO 9001 §7
A-2
How often should cube tests be conducted on an RMC pour?
How often should cube tests be conducted on an RMC pour?
Sampling frequency depends on the quantity of concrete placed. IS 456:2000 Cl. 15.2 and IS 516 (Part 1/Sec 1):2018 specify that for each grade of concrete, samples shall be taken at the rate of one sample per 50 m³ (or part thereof) of each grade placed, with higher frequency for controlled concrete per Cl 15.2.2. For very large pours, samples are also taken at hopper and at discharge. Each sample yields three 150 mm cubes tested at 28 days for acceptance (7-day cubes are additional and informative). Try the calculator: Sampling Planner.
Reference: IS 456:2000 Cl. 15.2 · IS 516 (Part 1/Sec 1):2018
A-3
What is the acceptance criteria for 28-day compressive strength as per IS 456?
What is the acceptance criteria for 28-day compressive strength as per IS 456?
Per IS 456:2000 Table 11 (Cl. 16.1 & 16.3), for specified grade M 15 and above, concrete is deemed to comply with the characteristic strength fck only when both of the following are met simultaneously: (1) the mean of any group of 4 non-overlapping consecutive test results is ≥ fck + 0.825 × established standard deviation (rounded to nearest 0.5 N/mm²), or ≥ fck + 3 N/mm², whichever is greater; and (2) every individual test result is ≥ fck − 3 N/mm². Note 1: until σ is established from 30 prior samples, use the assumed values from IS 456 Table 8. Note 2 (small-quantity rule): where concrete placed is up to 30 m³ and the number of samples is less than 4, the mean of all such samples shall be ≥ fck + 4 N/mm² and individual results ≥ fck − 2 N/mm²; if only one sample is taken, it shall be ≥ fck + 4 N/mm². Try the calculator: Cube Test Statistics.
Reference: IS 456:2000 Table 11 (Cl. 16.1 & 16.3)
A-4
How many cubes should be cast per sample as per IS 516?
How many cubes should be cast per sample as per IS 516?
Each sample of concrete is divided into three specimens of 150 mm cubes. The average strength of the three specimens represents the test result, provided no individual cube deviates by more than ±15% of the average. The specimens are typically tested at 7 days (informative) and 28 days (acceptance).
Reference: IS 516 (Part 1/Sec 1):2018
A-5
What is the role of a Quality Plan in construction projects?
What is the role of a Quality Plan in construction projects?
A Quality Plan (QAP) is a project-specific document that identifies what will be controlled, the standards it must meet, who is responsible, the procedures to follow, and records to retain. For concrete, the QAP typically covers incoming material tests, mix design approval, batching, placement, sampling frequency, testing, non-conformance handling, and final handover documentation.
Reference: IS 456:2000 Cl. 10 · ISO 9001 §7.5
A-6
How is compressive strength tested as per IS 516?
How is compressive strength tested as per IS 516?
IS 516 (Part 1/Sec 1):2018 prescribes: cube size 150 mm (or 100 mm for aggregate ≤20 mm), curing at 27 ± 2 °C in clean water, loading rate of 120 to 240 kg/cm² per minute (≈12 to 24 MPa/min) per IS 516 (Part 1/Sec 1):2018, which specifies 0.3 ± 0.1 N/mm²/s, and capping with self-neat cement paste to ensure parallel loading faces. Test age is normally 7 and 28 days; results are reported to the nearest 0.5 MPa.
Reference: IS 516 (Part 1/Sec 1):2018 §5–§6
A-7
What are common causes of low cube strength and how are they investigated?
What are common causes of low cube strength and how are they investigated?
Investigate in this order: (1) sampling error — wrong sample location or non-representative mix; (2) specimen defect — poor compaction, damaged moulds, improper curing; (3) mix issue — w/c ratio drift, cement quality, admixture overdose, aggregate moisture; (4) testing error — machine calibration, capping, loading rate. Retest before any structural consequence — and check 7-day results on the same sample for a pattern.
Reference: ConcreteInfo diagnostic checklist
A-8
How should concrete cubes be cured before testing?
How should concrete cubes be cured before testing?
After casting, keep cubes in the mould for 24 ± 0.5 h at ≥16 °C and shielded from vibration. Strip the cubes, mark them, and fully immerse in clean, fresh water at 27 ± 2 °C until just before testing. The water must be renewed every 7 days; do not allow cubes to dry. Curing is the single biggest controllable variable in cube results.
Reference: IS 516 (Part 1/Sec 1):2018 Cl. 5.4 · IS 456:2000 Cl. 13.5
A-9
What is the difference between trial mixes and approved mix designs?
What is the difference between trial mixes and approved mix designs?
A trial mix is the investigation — done in a lab using representative materials to achieve the target strength, workability and durability. An approved mix design is the documented selection of one successful trial mix with the actual material quantities, signed off by the structural designer / owner’s engineer for use in production. Trials without approval have no project status; approvals without trials have no evidence base. Try the calculator: Trial Mix Batch.
Reference: IS 10262:2019 §5 · IS 456:2000 Cl. 9
A-10
How are non-conformities (NCRs) documented and closed?
How are non-conformities (NCRs) documented and closed?
Issue a Non-Conformance Report (NCR) as soon as the deviation is observed — describe what happened, where, when, by whom witnessed, the specification or procedure violated, and the immediate containment. The NCR is then dispositioned (use-as-is, rework, repair, reject) with a clear root-cause action. Closure requires both the corrective action taken and the preventive action for the next pour.
Reference: ISO 9001 §10.2 · IS 456:2000 Cl. 16 & 17
Calculators for this category
All answers live in one searchable FAQ — use the search box to match your exact situation, or jump straight into a category.
Open the full FAQ