Why this calc exists
Sampling is the boring-but-critical first link in the acceptance chain. Too few cubes and a bad pour gets through; too many and the lab is overwhelmed. IS 456 Cl 15.2.2 gives a frequency band that depends on pour size and grade, but the language ('samples of 6 cubes each') doesn't tell you exactly how many samples YOUR pour needs.
The rules: 1 sample per 5 m³ for pours up to 30 m³; 1 sample per 10 m³ for 30–150 m³; for pours > 150 m³, the rate depends on the designer. For grades M30+, the designer may specify tighter sampling (some consultants double the frequency). The Sampling Planner calculator takes the pour volume, grade, and acceptance regime, and returns the cube count + sampling schedule.
Code references (with provenance)
- IS 456 Cl 15.2.2 — Sampling rate: 1 sample per 5 m³ up to 30 m³, 1 per 10 m³ up to 150 m³, ≥ 1 per pour.
- IS 456 Cl 15.2.2 Table 12 — Sample size: 6 cubes per sample (3 for 7-day, 3 for 28-day acceptance).
- IS 456 Table 11 — Conformity criteria the samples feed into.
- IS 456 Cl 16.1 — Strength acceptance criteria.
Worked: 60 m³ M25 pour
Cl 15.2.2 sampling rate: 60 m³ is in the 30–150 m³ band → 1 sample per 10 m³ = 6 samples.
Cubes per sample: 6 cubes × 6 samples = 36 cubes for this pour.
Lab workload: 36 cubes cast, 18 tested at 7 days, 18 at 28 days.
Cost: cube casting ~₹50 each (mould, casting, breaking) → ₹1,800 for this pour.
For an 8 m³ M25 pour: 1 sample per 5 m³ + ≥ 1 per pour → 2 samples → 12 cubes.
Field notes (what trips people up)
- M30+ often doubles the rate. Some specifications (especially for infrastructure projects) require 2 samples per 10 m³ for M30 and above. Check the project spec.
- One sample ≠ one cube. A sample is 6 cubes, period. Three go to 7-day, three to 28-day. Both subsets must independently meet acceptance.
- Site lab capacity. A 36-cube pour is a half-day in the lab for casting + a full day for breaking. Plan lab capacity against the pour schedule.
- Small pours are not exempt. Even a 3 m³ pour needs at least 1 sample = 6 cubes. The cube cost is a tiny fraction of the pour cost — don't skip.
Worked example
Site: 1,200 m³ podium slab pour, M40 grade.
Project spec: 2 samples per 50 m³ (double the IS 456 default for M40).
Samples: 1,200 / 50 × 2 = 48 samples.
Cubes: 48 × 6 = 288 cubes. Lab capacity: 9 cubes per testing day at 7 and 28 day → schedule lab time over 2 days per age.
FAQ
Why 6 cubes per sample?
3 for 7-day + 3 for 28-day. Each age subset is itself a mini-sample that the acceptance criterion applies to (mean of 3 ≥ fck + 4 for that age). If a single cube fails, the other 2 are still averaged — giving a fairer picture than 1 cube = 1 result.
What if I want to do only 7-day tests?
Possible but not advisable. 7-day is a leading indicator; 28-day is the contract acceptance. The cube cost is dominated by casting (~₹25), not testing (~₹25), so saving the 28-day set is false economy.
How does this fit with the acceptance criteria calc?
The sampling planner tells you HOW MANY cubes; the cube test statistics calc takes the cube results and checks against IS 456 Table 11. Use them sequentially: plan → cast → break → evaluate.