← Back to BlogRMC Plant Logistics · FLEET MATH · 29 SEP 2026
RMC Plant Logistics · IS 4926 Cl 5.2.2.1

Truck Cycle
Time & Fleet
Sizing.

Plant-to-pour math for dispatchers. The 2-hour discharge clock, cycle-time decomposition, fleet sizing formula, and why wait time at site is the worst problem on the diagram.

AH
Amit Haridas
Founder · ConcreteInfo
| September 29, 2026| 12 min read
TRUCK CYCLE TIME PLANT → SITE → PLANT · IS 4926 Cl 5.2.2.1 PLANT SITE 10m LOAD 35m TRAVEL 20m WAIT! 12m DISCH. 30m RETURN CYCLE TIME = 107 MIN LOAD 10 + TRAVEL 35 + WAIT 20 + DISCH 12 + RETURN 30 DISCHARGE LIMIT 120 min · IS 4926 Cl 5.2.2.1 ≤ 120 min ASTM C94 · ACI 304R · Plant cycle 7-9 trips / truck / day

Codes referenced

IS 4926:2003 Cl 5.2.2.1
Discharge within 2 h of loading

Concrete shall be discharged from the truck-mixer within 2 hours of loading. Longer period allowed with retarders / cool / humid / chilled conditions.

IS 4926:2003 Cl 5.2.2.2
Time of loading definition

Time of loading starts from adding water to the dry mix, or adding cement to the wet aggregate — whichever applies.

IS 4926:2003 Cl 6.2.1
30-minute site-prep delay rule

If discharge from the producer's vehicle is delayed at site for lack of purchaser preparedness, responsibility passes after 30 minutes.

ASTM C94/C94M-24
90-minute delivery limit (default)

Concrete shall be discharged within 90 min of batching unless the producer documents that a longer time does not adversely affect the concrete.

Cycle time decomposition

A truck cycle has five segments. The first three (load, travel, return) are plant-controllable; the last two (wait, discharge) are largely site-controlled. Two numbers are non-negotiable:

SegmentTypical durationControllable byVariability
Loading (charge + mix ≥60 rev)8–12 minPlantLow
Travel to site (10 km urban)25–45 minDispatcher / routeMedium
Wait at site0–60 minSite supervisorVery high
Discharge (chute or pump)10–15 minSite / pump crewLow
Return (empty)20–35 minDriverLow–medium
Total60–165 min (typical 90–110)—Driven by wait

Reference: ConcreteInfo RMC operations experience; IS 4926:2003 §5.2.2.1 (discharge limit), §6.2.1 (30-min site-prep delay); ACI 304R Guide for Measuring, Mixing, Transporting, and Placing Concrete.

Code Reference

IS 4926 Cl 5.2.2.1 & Cl 5.2.2.2 — the 2-hour discharge clock

These two short clauses set the absolute outer limit on a transit mixer's useful life. They tie plant operations to the dispatch clock:

  • "Concrete shall be discharged from the truck-mixer within 2 h of the time of loading. However, a longer period may be permitted if retarding admixtures are used or in cool humid weather or when chilled concrete is produced."
  • "The time of loading shall start from adding the mixing water to the dry mix of cement and aggregate or of adding the cement to the wet aggregate whichever is applicable."

Source: IS 4926:2003 §5.2.2.1 and §5.2.2.2. Verified against the BIS reprint.

Fleet sizing formula & worked example

The arithmetic is small but the input numbers matter. The base formula:

Trucks needed = ⌈ (Pour rate × Cycle time) ÷ Truck capacity ⌉ + standby

A standby of one truck is added to absorb breakdowns, traffic and queueing variance.

40 m³/h

Pour rate 40 m³/h, 90-min cycle, 7 m³ trucks

Typical urban mid-rise slab pour

Plugging in: (40 × 1.5) ÷ 7 = 8.57 → round up to 9 trucks, plus 1 standby → 10 trucks. At 7 m³ per trip and 7 trips per truck per day, this fleet can deliver ~490 m³/day, which is enough for an 8-hour pour at 40 m³/h with margin.

Pour rateCycle timeTruck capacityCalculated trucksWith 1 standby
30 m³/h60 min (highway)7 m³4.3 → 56
40 m³/h90 min (urban)7 m³8.6 → 910
50 m³/h90 min (urban)7 m³10.7 → 1112
50 m³/h120 min (bad traffic)7 m³14.3 → 1516
80 m³/h75 min (highway)9 m³11.1 → 1213

Reference: ACI 304R; ConcreteInfo fleet-model templates. All cycles assumed inclusive of 15-min wait at site.

Plant utilisation rule of thumb — 70–75 %

A plant's nameplate capacity is the theoretical maximum at zero downtime. In practice:

Plant nameplateRealistic sustained (70–75 %)Notes
30 m³/h21–23 m³/hCompact plant, single mixer
60 m³/h42–45 m³/hMid-size commercial plant
90 m³/h63–68 m³/hTwin-mixer or large single
120 m³/h84–90 m³/hTwin-mixer highway project

The lost 25–30 % comes from aggregate bin refill, cement silo refill pauses, moisture probe drift, truck queuing, mixer truck arrival pattern, and QA sampling. A plant claiming sustained output at >80 % of nameplate over a week is either over-specified or under-recorded.

Urban vs highway — the geography factor

Travel segment is the second-largest contributor to cycle time, and it changes with route type:

Route type10 km each way25 km each waySpeed assumption
Dense urban (Mumbai, Pune old city)45 min90–110 min15 km/h avg
Suburban arterial25 min50–60 min25–30 km/h avg
Highway / expressway10–12 min22–28 min60–80 km/h avg

A 40 m³/h pour with 7 m³ trucks takes 9 trucks on a 90-min urban cycle, 6 trucks on a 60-min highway cycle. The fleet needed to deliver the same pour halves as soon as the highway opens. This is why dispatchers care about the route map more than the pour schedule.

Why wait time at site is the worst problem

In the cycle-time breakdown above, three of the five segments are reasonably predictable from past data. The fourth — wait time at site — is where 60 % of all delivery-failure complaints originate. Causes include:

  • Formwork or rebar inspection delayed — pour slot missed because the engineer is on another floor.
  • Pump not ready — boom not positioned, pipeline not primed, prime-line grout already set.
  • Previous truck still discharging — chute stuck, pump blocked, downstream placement team short-handed.
  • Pour paused for cube result — site insists on a 7-day cube from an earlier load before pouring further.
  • Site access blocked — barricade up for crane lift, chhath puja road closure, waterlogged access ramp.

Every minute of waiting is two losses: a minute the next truck cannot be loaded, and a minute closer to the 2-hour discharge clock of IS 4926 Cl 5.2.2.1. IS 4926 Cl 6.2.1 makes the site responsible after a 30-minute delay caused by lack of purchaser preparedness — but the load may already be lost by then. The plant's only direct control is the 30-minute call-ahead, the agreed pour-window in the PO, and a printed site-readiness checklist sent to the site supervisor the day before.

Multi-site batching strategies

When two sites are pulling from the same plant, the dispatcher must avoid both being short at the same moment. Three standard responses:

Time-window split

Site A receives 06:00–10:00, Site B receives 10:30–14:30, with a buffer pour at each end. Plants with single batch panel often default to this.

Plant-share split

Trucks are colour-coded or assigned; a fixed ratio of trucks runs to each site. Requires discipline, but prevents the loudest site from starving the quiet one.

Pour-rate priority

The faster pour rate gets the first wave; once its pour rate is met, the slower site gets the remainder of the fleet. Use only when both sites accept variable start times.

Common dispatch failures

· Fleet sized for ideal cycle, not median

Dispatcher computed fleet on 60-min cycle. Average cycle over the month is 95 min. Result: chronic 30-min waits, late deliveries, rejected loads. The fix: use median cycle from the last 30 days, not the best-day cycle.

· No standby truck in the plan

One truck breaks down. Pour falls 1/10th behind immediately. Crew overruns into evening. The fix: one standby is non-negotiable above 8 trucks.

· 2-hour limit not tracked live

Driver waits 75 min at site. Truck was loaded 90 min ago. Pour is still 5 min away. The fix: dispatch software shows clock per truck; driver calls when 90 min is reached even if waiting.

· Plant output assumed at nameplate

60 m³/h plant + 90-min cycle + 7 m³ truck = (60 × 1.5)/7 = 12.9 trucks for 60 m³/h pour. But the plant never actually delivers 60 m³/h. Real fleet needs to match realistic sustained output, not the brochure.

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how the cycle-time model resolves into a decision: hire another truck, or change the route, the pour window or the plant's stated output.

Questionnaire — asked at the dispatch desk, before the day's fleet is committed

  1. What is the median cycle time from the last 30 days? Not the best day, not the brochure figure. Sizing on the best-day cycle is how a plant ends up with chronic waits.
  2. What pour rate is being committed, in m³/h, and over what window? The rate and the window are what the truck count has to serve.
  3. What truck capacity is on the order? 7 m³ and 9 m³ fleets behave very differently against the same pour.
  4. Is the plan built on the plant's nameplate, or on its sustained output? Realistic sustained output is 70–75% of nameplate. Anything above 80% sustained over a week is over-claimed.
  5. Does the fleet include one standby truck? One standby is non-negotiable above 8 trucks.
  6. What is the route type? For 10 km, a dense urban run is 45 min, a suburban arterial 25 min, a highway 10–12 min. The route decides the fleet.
  7. Who confirms site readiness, and is there a call-ahead 30 minutes before arrival? That is the only direct control you have over the wait.
  8. Is the 2-hour clock tracked live per truck, from water addition onwards? IS 4926:2003 Cl 5.2.2.1 with Cl 5.2.2.2, and the driver's own call at 90 minutes even while waiting.

Inspector's checklist — what to verify on site

  1. Fleet size computed and written down with the arithmetic showing: pour rate × cycle time ÷ truck capacity, rounded up, plus one standby.
  2. Cycle time built from the five segments, not from a single round number: loading 8–12 min, travel 25–45 min on a 10 km urban run, wait 0–60 min, discharge 10–15 min, return 20–35 min.
  3. The standby truck rostered and physically available, not a name on a list at the plant office.
  4. Dispatch screen showing elapsed time per truck from the moment of loading, with the driver instructed to call at 90 minutes even if the truck is still waiting at site.
  5. Site-readiness checklist sent to the site supervisor the day before the pour, with the agreed pour window in the purchase order and a 30-minute call-ahead built into the run sheet.
  6. Multi-site days worked on one of the three standard splits (time-window, plant-share, pour-rate priority), recorded so nobody improvises at 14:00 when both sites are short.
  7. Refused and returned loads logged against the delivery, so the cycle time in the model keeps matching what actually happened on the ground.
  8. Site-caused delays over 30 minutes recorded, because responsibility passes to the purchaser after that point under IS 4926:2003 Cl 6.2.1, and only a record will prove it.

What happens if… three worked examples

Example 1 — a 40 m³/h pour on a 90-minute urban cycle with 7 m³ trucks

What happens. The formula gives (40 × 1.5) ÷ 7 = 60 ÷ 7 = 8.57, so 9 trucks after rounding up, plus 1 standby, so 10 trucks. At 7 m³ per trip and 7 trips per truck per day that fleet can deliver about 490 m³/day (10 × 7 × 7), against an 8-hour pour of 40 × 8 = 320 m³. The fleet has margin.
Likely outcome. The pour is served without a truck queue, provided the wait at site stays inside the 15 min the calculation assumed. Note where the assumption came from: the median cycle of the last 30 days. Run the same arithmetic on a best-day 60-minute cycle and you come out with 7 trucks against the 10 you actually need, which is how a plant gets chronic 30-minute waits, late deliveries and rejected loads.

Example 2 — the same pour, the same trucks, a highway route instead

What happens. On a 60-minute cycle, (40 × 1.0) ÷ 7 = 5.71, so 6 trucks after rounding up, plus 1 standby, so 7. The calculated count for the same 40 m³/h pour falls from 9 on the urban cycle to 6 on the highway cycle, on route choice alone, before anybody buys a vehicle. The travel segment is the second-largest term in the cycle, and it is the one you can change.
Likely outcome. Route selection beats truck purchase, every time. And if the wait at site comes down by 15 minutes, that saves roughly one more truck, which is why dispatchers care about the route map more than the pour schedule.

Example 3 — the fleet is sized on a 60 m³/h plant that has never made 60 m³/h

What happens. On nameplate, (60 × 1.5) ÷ 7 = 90 ÷ 7 = 12.86, so 13 trucks. But 70–75% of 60 m³/h is 42–45 m³/h of realistic sustained output, and at 42 m³/h the count is (42 × 1.5) ÷ 7 = 63 ÷ 7 = 9, so 9 trucks plus 1 standby, so 10.
Likely outcome. The honest number is 10, not 13. Sizing on nameplate buys three trucks that stand idle while the plant loses 25–30% of its nameplate to bin refills, silo pauses, probe drift, queueing and QA sampling. A plant claiming sustained output above 80% of nameplate over a week is either over-specified or under-recorded.

Frequently Asked Questions

What is the maximum transit time for RMC concrete per IS 4926?
IS 4926 Cl 5.2.2.1 states that concrete shall be discharged from the truck-mixer within 2 hours of the time of loading. The clock starts at the moment water is added to the dry mix of cement and aggregate, or at the moment cement is added to the wet aggregate — whichever is applicable (Cl 5.2.2.2). A longer period may be permitted if retarding admixtures are used or in cool humid weather or when chilled concrete is produced. ASTM C94 specifies a similar 90-minute limit on the elapsed time between batching and discharge unless the producer can demonstrate that a longer time does not adversely affect the concrete.
How many trucks are needed for a 50 m³/h pour?
Trucks needed = (Pour rate m³/h × Cycle time h) ÷ Truck capacity m³. For a 50 m³/h pour with a 90-minute cycle and 7 m³ trucks: (50 × 1.5) ÷ 7 = 10.7, rounded up to 11 trucks. In practice, add one standby truck to absorb breakdowns and waiting delays, so the fleet becomes 12 trucks. A 50 m³/h pour with a 60-minute cycle and the same 7 m³ trucks needs only (50 × 1.0) ÷ 7 = 7.1, rounded up to 8 trucks. Cycle time is the dominant lever — every 15 minutes of reduction in wait time at site saves roughly one truck.
Why is wait time at site the worst problem for truck cycle time?
Loading, travel and discharge are reasonably predictable from past data — a 10 km urban run is 25–45 min, a 7 m³ load takes 8–12 min to charge, and discharge itself is 10–15 min. Wait time at site is the segment that varies from 0 minutes to 60 minutes on the same day: pump not ready, formwork inspection delayed, previous truck still discharging, concrete-pump blockage. Every minute of waiting is a minute the next truck cannot be loaded, and a minute closer to the 2-hour discharge limit per IS 4926 Cl 5.2.2.1. The plant cannot control it directly — only the dispatch phone call 30 minutes before arrival, the agreed pour-window discipline, and a pre-pour site checklist can pull this number down. Without that, fleet size has to be padded by 15–25 % to absorb the wait-time variance.

Related articles

AH
About the author

Amit Haridas

Founder & Proprietor, ConcreteInfo. 25+ years experience in construction QA/QC, concrete technology, RMC plant operations, consulting and technical training across India. For dispatch-software setup, fleet sizing templates, or dispatcher training, contact amit@concreteinfo.in.

Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.

Need hands-on help?

Reading is one side.
Dispatching is the other.

If the cycle-time math here matches what your dispatchers live with, our RMC operations audits and dispatcher training programmes cover the rest.