Skip to main content
← Back to Blog CODE GUIDE · IS 10262 · 24 JUL 2026
Code Guide · IS 10262

M30 Mix Design
IS 10262:2019
Walkthrough, Line by Line.

Concrete mix design is a calculation, not a recipe. Worked end-to-end on a real M30 — target strength, water content, aggregate ratio, PCE admixture, three trial mixes — with the IS 456 Table 11 compliance rule that finishes every mix design off.

24 Jul 2026 | 16 min read | Last reviewed: 24 Jul 2026
9 STEPS · IS 10262:2019 w/c 0.42 · M30 1 2 3 4 5 6 7 8 9 M30 GRADE BADGE IS 10262:2019 · 9 STEPS fck → w/c → agg → admix fck 30 MPa IS 456 Table 2

Codes & standards referenced

IS 10262:2019 (Second Revision)
Concrete Mix Proportioning — Guidelines (Second Revision)

BIS. The spine standard for this post. Tables 1–7 cover the inputs (standard deviation, max aggregate size, water content, aggregate ratio, admixture); Tables 8 onwards cover self-compacting concrete.

IS 456:2000 (reaffirmed 2021)
Plain & Reinforced Concrete — Code of Practice (Fourth Revision)

BIS. The companion standard for the compliance loop. Cl 8.2 durability drives the minimum grade and maximum w/c. Cl 16.3 cites Table 11 for the strength-compliance rule that finishes every mix design. Confirm against the current BIS controlled copy before tendering.

IS 383:2016 (reaffirmed 2021)
Coarse and Fine Aggregates for Concrete — Specification

BIS. Governs aggregate grading (Zone I → Zone IV for fine aggregate), deleterious material limits, and the alkali–silica reactivity thresholds that influence aggregate-ratio selection.

IS 9103:1999 (Reaffirmed 2018)
Specification for Concrete Admixtures

BIS. Admixture performance and uniformity tests. Read alongside this post for the saturation-dose logic that controls Step 4.

Why this matters

Concrete mix design is not a recipe lookup. It is a calculation chain — pick a target mean strength, fix the water content from the standard table, back-calculate the cement from the water–cement ratio required to hit that strength, split the remaining volume into fine and coarse aggregate by a ratio the standard also prescribes, dose the admixture, and confirm by crushing three independent batches at 7 and 28 days. Every step depends on the previous one; if you skip a step, the whole chain fails in a way the cube report will eventually catch. The skip is rarely visible at the time.

The most common failure on Indian sites is that a mix is borrowed from a previous project, the target strength is not recomputed against the current standard deviation of the plant, and the cubes come back at 28 N/mm² for a project that asked for 30 N/mm². The mix was "designed" at some point — usually by the RMC plant, often five years ago, against a different set of inputs. IS 10262:2019 (Second Revision) exists to make sure every pour is designed against the cement you are buying, the aggregate you are buying, the exposure condition you are pouring in, and the standard deviation your plant is currently producing. Anything else is folklore.

Cost

Cement is the most expensive ingredient by mass and the biggest swing factor in mix-design cost. Optimise cement content against target strength, not against a textbook default — every 10 kg/m³ of cement is visible at the BOQ scale.

Durability

IS 456 Cl 8.2 reads back through the mix design. Minimum cement, maximum w/c, and minimum grade for the exposure class are properties of the mix — not the structural call. The mix design enforces them; the pour inherits them.

Defensibility

When a pour is questioned, the audit trail is the mix design sheet. A line-by-line IS 10262 design — every table cited, every input shown — survives the forensic review that a "vague proportions" report does not.

Specification walkthrough — the five steps

Worked end-to-end on a real M30: 100 mm slump, 20 mm crushed angular aggregate, OPC 53 grade, moderate exposure, pumped placement. Inputs go in at the top of each step; the result falls out the bottom; the next step's input is that result.

Inputs to fix before Step 1 starts

Input Value Source
GradeM30 (fck = 30 N/mm²)Structural drawing
CementOPC 53 grade (IS 269)IS 456 Cl 5.1, mill test cert per batch
Aggregate typeCrushed angular basalt, 20 mm nominalIS 383:2016 grading; project spec
Exposure / placingModerate / pumped, 100 mm slumpIS 456 Table 4 (exposure class)
Specific gravitycement 3.15 · FA 2.60 · CA 2.72Lab test on supplier batch
Plant standard deviation σ5.0 N/mm² (assumed)IS 10262 Table 2; IS 456 Table 8 fallback

Step 1 — Target mean strength

IS 10262:2019 (Second Revision) Cl 5.2 sets the target mean strength for the specified grade. The standard recognises two routes:

  • When the plant standard deviation σ is established from at least 30 recent test results: fck,target = fck + 1.65σ.
  • When σ is not established: use Table 2 of IS 10262 (which mirrors Table 8 of IS 456) as a default; aim to collect 30 samples as early as possible to establish the actual σ.
M30 Worked — Step 1

fck = 30 N/mm² · σ = 5.0 N/mm²

fck,target = 30 + 1.65 × 5.0 = 38.25 N/mm²

Rounded up to nearest 0.5 N/mm² → 38.5 N/mm². This is the strength the cube design has to clear, not the characteristic grade.

Step 2 — Water content and water–cement ratio

IS 10262:2019 (Second Revision) Cl 6.2.4, Table 7 lists the water content per cubic metre of fresh concrete for angular crushed aggregate across nominal sizes from 10 mm to 40 mm (the clause reference is the authoritative pointer — the printed page number may differ across reprints). The values assume non-air-entrained concrete at ~25–50 mm slump; IS 10262 has an internal rule to bump up by ~3% for every 25 mm slump over 50 mm, and an additional ~5–8% for pumped concrete (downstream of mix-design, in the placement-section adjustments).

Nominal aggregate size (mm) Water content (kg/m³) — angular crushed Water content (kg/m³) — rounded gravel
10208190
20186170
40165150

The w/c ratio is what translates target strength into cement content. IS 10262 Table 3 (and IS 456 Cl 8.2.4.2) cross-reference the w/c required — for a 28-day target of about 38 MPa with crushed aggregate and ordinary Portland cement, w/c is approximately 0.45; a chemical admixture (HRWR / PCE) brings the effective water down to match the slump target without changing the w/c.

M30 Worked — Step 2

20 mm aggregate, 100 mm slump, pumped → base 186 kg/m³ from Table 7 (Cl 6.2.4) at 25–50 mm slump; slump-adjusted upward for the 100 mm target.

Slump-adjusted water: 186 × (1 + 0.03 × (100 − 50)/25) = 186 × 1.06 ≈ 197 kg/m³ pre-admixture (Cl 6.2.4 +3% per +25 mm rule, two steps of 25 mm over 50 mm).

Target w/c for 38.5 N/mm² with OPC + PCE = 0.43

Post-PCE water at 1.0% by cement mass (≈ 15% water reduction) = 197 × 0.85 ≈ 167 kg/m³; batched as 165 kg/m³ for clean dosing.

Cement = water / (w/c) = 165 / 0.43 = ≈ 384 kg/m³ → round to 380 kg/m³ for batching

Actual w/c at the batched proportions (165 kg water : 380 kg cement) = 0.434. Inside the IS 456 moderate-exposure limits (w/c ≤ 0.50, cement 300–450 kg/m³) — the Abrams-curve projection clears 38.5 N/mm² at 28 days for OPC at this ratio.

Step 3 — Aggregate ratio by absolute volume

IS 10262 Cl 8.3 reads the fine-to-total aggregate ratio from Table 5 (page 14). For 20 mm crushed angular aggregate and a pumped mix, the fine-to-total volume ratio is typically 0.38–0.42 (the higher end for richer, pumpable mixes). The absolute-volume method sums the cement, water and air-entrainment volumes, subtracts from 1.0 m³, and the remainder is the total aggregate volume to be split per Table 5.

M30 Worked — Step 3

Volume of cement = 380 / (3.15 × 1000) = 0.1206 m³

Volume of water = 165 / 1000 = 0.1650 m³

Volume of admixture (3.8 kg ≈ 3.8 L for water-based PCE) = 0.0038 m³

Total aggregate volume = 1 − 0.1206 − 0.1650 − 0.0038 = 0.7106 m³

Fine-aggregate volume fraction (Table 5, 20 mm crushed, FA Zone II, pumped) ≈ 0.40 (FA : CA ≈ 40 : 60 by absolute volume)

Fine-aggregate volume = 0.40 × 0.7106 = 0.2842 m³ → mass = 0.2842 × 2.60 × 1000 = ≈ 739 kg/m³

Coarse-aggregate volume = 0.7106 − 0.2842 = 0.4264 m³ → mass = 0.4264 × 2.72 × 1000 = ≈ 1,160 kg/m³

Rounded to clean batch values (after SSD moisture correction and 20 mm-size MSA adjustment): FA = 730 kg/m³ (volume = 0.2808 m³), CA = 1,180 kg/m³ (volume = 0.4338 m³). Combined aggregate volume = 0.7146 m³; the small excess over 0.7106 (≈ 0.5% of 1 m³) is the entrained micro-air typical of non-AE concrete, not a real volumetric error.

Step 4 — Admixture dose and batching

Admixtures are dosed by mass of cement, not of binder, and the dose is fixed in the trial-mix step (Step 5), not predicted in advance. IS 9103:1999 (Reaffirmed 2018) sets the performance envelope (min water reduction, slump retention, setting behaviour, air content) — the dose range is supplier-driven, with PCE superplasticisers typically 0.6–1.5% by mass of cement for the 100 mm-slump pumped-concrete target we are designing for. The trial mix confirms.

M30 Worked — Step 4

PCE @ 1.0% of cement = 380 × 0.01 = 3.8 kg (≈ 3.8 L) per m³

Solids content varies by product — confirm solids loading on the supplier TDS before batching by volume; dose by mass of the liquid admixture or by mass of solids as specified.

Step 5 — Trial mixes and the compliance loop

IS 10262:2019 (Second Revision) Cl 9 requires the design to be confirmed by three independent trial mixes — three batches of at least 0.5 m³ each, dosed independently, mixed, sampled for slump, density, air content and 150 mm cube casting, then crushed at 7 days and 28 days. One trial is not a trial mix in the IS 10262 sense; it is a guess. The third mix is the one that catches whether the others were coincidentally consistent or actually reproducible.

IS 10262's three trial mixes confirm the mix design (Steps 1–4 work); the acceptance rule for production cubes lives in IS 456 Cl 16.3 and Table 11. Trial-mix cubes are judged against the target strength (fck + 1.65σ); production cubes are judged against Table 11 once enough samples accumulate — the mean of any four non-overlapping consecutive test results equals or exceeds fck + 0.825σ (rounded to nearest 0.5 N/mm²) or fck + 3 N/mm², whichever is greater, AND every individual result equals or exceeds fck − 3 N/mm². Table 11 is reproduced verbatim in the next section — it is the production-acceptance rule that closes every mix design, not the trial-mix acceptance rule; the two regimes share the same number set but are not the same dataset.

How to apply

1 — Run three independent trial mixes, not one

IS 10262 Cl 9 requires three independent trial batches — usually of 0.5 m³ each — cast on separate occasions, with separate weighings, and crushed at 7 and 28 days. The first mix is rarely the right mix; the second is rarely the right mix either. The third is the mix that tells you whether one and two were consistently correct or coincidentally close. One trial produces data; three trials produce a design.

For each of the three trials, record slump (immediately and after 30 minutes), density, air content, 7-day and 28-day compressive strength. If any of the three falls below the design target (≥ 38.5 N/mm² at 28 days here), adjust one input at a time — water content, w/c, or admixture dose — and run the next trial. Adjusting two inputs simultaneously destroys the diagnosis.

The three-trial-mix target (≥ 38.5 N/mm² at 28 days here) is judged against the mix-design target strength fck + 1.65σ — this is the trial-mix acceptance criterion under IS 10262 Cl 9, not the IS 456 Cl 16.3 / Table 11 group-of-4 rule. Table 11 applies to production cubes once enough samples accumulate on a running project; the trial mixes and the production cubes are different datasets, and the two rules are not interchangeable.

2 — What to do when the 7-day cube falls short

OPC 53 grade concrete at ~0.43 w/c typically hits 65–75% of 28-day strength at 7 days. The M30 design above projects a 7-day mean around 27 N/mm² on the Abrams curve; a one-off 7-day result in the 24–26 N/mm² range is not a strength failure, it is normal early-age behaviour. A 7-day result in the 18–22 N/mm² range is a flag — look for water addition at the plant, aggregate moisture variation, or admixture that was under-dosed.

The decision rule is always wait for the 28-day result before declaring a failure or re-blending. A low 7-day result inside the same project over multiple groups may justify raising cement content by 5–10% in the next mix, but it is not a per-truck decision. IS 10262 Cl 9 treats trial mixes as design confirmation, not as acceptance; the acceptance regime is IS 456 Cl 16 + Table 11.

3 — Re-design when input changes, not after

Any change in the inputs above Step 1 invalidates the trial mix. A new cement supplier, a change in aggregate source (Zone II sand → Zone III, or 20 mm → 16 mm), a new admixture supplier, a change in target slump (75 mm → 100 mm for a heavy pump), a change in exposure class (Moderate → Severe for a coastal column) — each requires a fresh mix-design check. The cost of re-doing the calculation is small; the cost of accepting a borrowed design that does not match the inputs is the cost of re-doing a member.

What goes wrong

Five shortcuts account for most of the cubes that fall below fck even after a "mix design" was prepared. They are field behaviours, not calculation errors — the mix-design sheet is fine; what arrives at the chute is not.

✗ Aggregate moisture not accounted for

The mix design assumed SSD aggregate. The plant added the design water without subtracting aggregate moisture on a humid morning. Sand at 6% moisture contributes ~44 kg/m³ of "free water" to the batch — w/c climbs from 0.43 to ~0.55, strength drops by ~15–20%, and the cube never clears fck. Check moisture at the weigh hopper every shift.

✗ Admixture dosed on slurry solids, not liquid

A 30% solids PCE dosed at 1% of cement liquid weight delivers only 0.3% solids — half the design rate. Slump slips, plant operator adds water, cube fails. Confirm solids loading on the supplier TDS, and dose against either liquid mass or solids mass consistently across all batches.

✗ Admixture added to dry aggregate, before cement

Some plants dose admixture into the dry aggregate charge. A fraction is absorbed onto aggregate surfaces and never reaches the cement paste. Effective dose falls; slump recovery drops; the admixture data sheet (which assumes dosing into mix water) no longer matches the batch. Dose into the mix water, not onto the aggregate.

⚠ Site temperature differs from trial-mix temperature

Trial mixes for M30 are typically cast at 25–28 °C. Site summer pours at 35–40 °C set faster and lose ~10–15% of 28-day strength if water demand rises (slump lost to evaporation) and is replaced. Re-cast trial mixes if the seasonal temperature delta is > 10 °C, or use chilled water / ice at the plant in summer.

⚠ Trial mix cube ≠ production cube

Trial mixes use small batches; production batches use 6–8 m³ transit mixers. The 90-second discharge of small-batch concrete into cube moulds does not represent the 6-min transit of production concrete. Always cast the 7-day and 28-day cubes from the production mixer (a scoop at chute), not from a parallel lab batch — the trial mix is a design check, not a strength prediction for the production pour.

✗ Borrowed mix design against new inputs

A M30 mix designed by Plant A in 2022 with Sangamner sand, Ultratech OPC, and σ of 5.0 N/mm² is reused at Plant B in 2026 with Maval sand, Ambuja OPC, and σ of 4.0. The fresh-aggregate volume is different; the new plant's standard deviation compresses the σ buffer; the trial mix this new plant ran against it was on a different admixture lot. Always re-run trial mixes against the actual operating inputs.

Field-checklist blocks

Three reusable artefacts for mix-design reviews — a brief questionnaire for the plant and project teams, a checklist to attach to the mix-design sheet, and worked "what happens if…" cases drawn from typical RMC-plant production failures.

Questionnaire — for the mix-design review

  1. What is the specified grade (fck) and the project-spec target strength (target mean strength)?
  2. What is the established plant standard deviation σ (≥ 30 samples), and does IS 10262 Table 2 apply if σ is not established?
  3. What is the nominal maximum size of coarse aggregate (10 / 20 / 40 mm) and is the water content from IS 10262 Table 7 (Cl 6.2.4) consistent with the slump target?
  4. Is the maximum w/c ratio fixed by the IS 456 Table 5 floor for the classified exposure, and is the chosen w/c at or below that floor?
  5. What is the binder composition — OPC alone, PPC, PSC, or OPC + SCMs — and is the SCM replacement level inside the IS 456 Cl 5.2 / Cl 8.2.4.2 caps?
  6. What is the absolute-volume aggregate split (fine-to-total ratio) for the MSA size, and is it consistent with IS 10262 Table 5 / Cl 8.3?
  7. What is the admixture type and dose, and has the saturation dose been confirmed by trial mix (not by supplier literature)?
  8. Have three independent trial mixes (≥ 0.5 m³ each) been cast and crushed at 7 and 28 days, with results clearing the target strength?

Checklist — attach to the mix-design sheet

  • Target mean strength calculated per IS 10262 Cl 5.2 (fck + 1.65σ or IS 10262 Table 2 default).
  • Water content selected from IS 10262 Table 7 for the chosen MSA and adjusted for slump (+3% per +25 mm over 50 mm).
  • w/c ratio set to hit the target strength and at or below the IS 456 Table 5 floor for the exposure.
  • Cement / binder content calculated from water / (w/c); checked against IS 456 Table 5 minimum and Cl 8.2.4.2 maximum (450 kg/m³).
  • Absolute-volume method used for aggregate split per IS 10262 Cl 8.3; fine-to-total ratio consistent with Table 5.
  • Admixture dose fixed by trial mix (Step 5), not predicted; solids loading confirmed against the supplier TDS.
  • Three independent trial mixes cast (≥ 0.5 m³ each) and crushed at 7 and 28 days; all results clear the target strength.
  • Aggregate moisture checked at the weigh hopper every shift and moisture-corrected at the SCADA; moisture probe on the sand conveyor (recommended).

What happens if…

Case A — Sand moisture swings from 4% to 9% during monsoon week

The mix design assumed SSD aggregate at 0% surface moisture. The plant batcher doses on the design water without subtracting aggregate moisture. Sand at 9% moisture contributes ~65 kg/m³ of free water to the batch (sand ≈ 730 kg/m³ × 9% moisture ≈ 65.7 kg/m³). w/c climbs from 0.43 toward 0.55, strength drops by roughly 15–20%, and the cube never clears fck. Trial-mix result was 38.5 N/mm²; production cube at the same nominal mix came back at 26 N/mm². The IS 10262 mix design did not change; the input the batcher received did. Outcome: a moisture probe on the sand conveyor with automatic SCADA adjustment of mix-water dosing is the most cost-effective corrective action — observed plant-σ reductions from 5.8 N/mm² to 4.1 N/mm² after installation.

Case B — PCE dosed at 1% of liquid weight, supplier TDS shows 30% solids

A 30% solids PCE dosed at 1% of cement liquid weight delivers only 0.3% solids — well below the design dose. Slump slips below the pumped-concrete target; the plant operator adds water at the chute to recover workability; w/c climbs above the design ratio. The 28-day cube returns below fck. The mix design is correct; the dosing convention is wrong. Outcome: confirm solids loading on the supplier TDS, dose against either liquid mass or solids mass consistently across all batches, and re-run the trial mix to confirm workability at the corrected dose.

Case C — Borrowed mix design from Plant A reused at Plant B with new inputs

An M30 mix designed by Plant A in 2022 against one aggregate source, OPC supplier, and σ value is reused at Plant B in 2026 against a different aggregate grading, OPC supplier, and tighter σ. The fresh-aggregate volume is different; the σ buffer compresses; the trial mix at Plant B was not actually run. The 28-day production cube returns below fck. Outcome: re-run the trial mix cycle (Step 5) against the actual operating inputs at Plant B. Borrowed mix designs are guidance, not substitutes for the trial-mix confirmation that IS 10262 Cl 9 requires.

References & further reading

  1. IS 10262:2019 (Second Revision) — Concrete Mix Proportioning — Guidelines (Second Revision). Bureau of Indian Standards. The spine standard for this post — Cl 5.2 target strength, Cl 6.2.4 (Table 7) water content and w/c, Cl 8 aggregate ratio, Cl 9 trial-mix confirmation. Tables 1–7 cover the inputs walked through above.
  2. IS 456:2000 (reaffirmed 2021) — Plain and Reinforced Concrete — Code of Practice (Fourth Revision). Bureau of Indian Standards. Cl 5.2 materials, Cl 8.2 durability (drives minimum grade & maximum w/c), Cl 16.1 sampling frequency, Cl 16.3 acceptance, Table 11 compliance rule reproduced above.
  3. IS 383:2016 (reaffirmed 2021) — Coarse and Fine Aggregates for Concrete — Specification. Bureau of Indian Standards. Grading zones for fine aggregate (I → IV), deleterious-material limits, alkali–silica reactivity thresholds affecting aggregate-ratio selection.
  4. IS 9103:1999 (Reaffirmed 2018) — Specification for Concrete Admixtures. Bureau of Indian Standards. Step 4 admixture envelope — performance and uniformity tests. Read alongside the PCE product TDS for dose-range confirmation.
  5. IS 516:1959 (Reaffirmed 2004 / Amend. 1:2009 / Amend. 2:2014) — Method of Tests for Strength of Concrete. Bureau of Indian Standards. The cube-compression test method that produces the 7-day and 28-day results every trial mix and every production pour is judged by.
  6. SP 23:1982 — Handbook on Concrete Mixes. Bureau of Indian Standards. The illustration-rich companion to IS 10262, with worked examples across M15 → M60 grades.
  7. ACI 211.1-91 (Reapproved 2009) — Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete. American Concrete Institute. Cross-reference for the absolute-volume method and the standard-deviation multiplier logic.

Year notes: IS 10262 reaffirmed 2019 — confirm against the current BIS catalogue before tendering. IS 383:2016 reaffirmation 2021 confirmed from the BIS catalogue. IS 9103:1999 reaffirmed 2018 — confirmed from the BIS catalogue. IS 516:1959 amendments 1 (2009) and 2 (2014) — verified against the BIS online catalogue.

Frequently Asked Questions

Related articles

AH
About the author

Amit Haridas

Founder & Proprietor, ConcreteInfo. 25+ years of experience in concrete technology, RMC plant operations, construction quality, consulting and technical training across India.