Skip to main content
← Back to Blog FIELD GUIDE · CUBE TESTING · 24 JUL 2026
Field Guide · Cube Testing

Cube Testing
Procedure as per
IS 516.

The single test that decides whether your concrete passed or failed. Sampling, casting, curing, testing, and what to do with the numbers — the complete site-engineer guide.

24 Jul 2026 | 20 min read | Last reviewed: 24 Jul 2026
COMPRESSION FRAME · 2000 kN 150 mm 315 kN/min fck 30 MPa target load 675 kN
Cube testing (IS 516) — 150 mm cube, capping plates, CTM with 14 MPa/min loading arrow A schematic compression testing machine shows a top platen, a top capping plate, a 150 mm concrete cube, a bottom capping plate and a bottom platen. An orange loading arrow with the label 14 MPa per minute indicates the IS 516 loading rate. CUBE TESTING (IS 516) — 150 mm cube · capping plates · 14 MPa/min loading CTM schematic top platen top capping plate 150 mm CONCRETE CUBE 22,500 mm² 150 mm bottom capping plate 14 MPa / min IS 516 loading rate CUBE TEST · KEY · 150 mm standard · capping ±0.05 mm · platen parallel · load 14 MPa/min · peak = failure · fc = P / A (MPa) · 7 / 28 day ages · 3 cubes per result IS 516 controlled copy governs
IS 516 cube strength is peak load divided by 22,500 mm², applied at 14 MPa per minute on a capped, parallel-faced 150 mm cube — every deviation is a deviation from the test.

Reference card — verified IS codes

Verified 2026-09-14 against ~/Standards library + BIS portal. ConcreteInfo reference card.

Codes referenced

IS 516 (Part 1/Sec 1):2021*
Methods of Tests for Hardened Concrete — Part 1 Strength Tests, Sec 1 Compressive, Flexural & Split Tensile

Sampling, casting, curing, and compressive strength testing of cubes.

IS 456:2000
Plain & Reinforced Concrete — Code of Practice

Clause 15 (sampling), Clause 16 (acceptance criteria — Table 11).

IS 1199 (Part 1):2018*
Methods of Sampling & Analysis of Fresh Concrete — Part 1 Sampling of Fresh Concrete

Sampling at the point of delivery / placement.

IS 10086:2021 (First Revision)
Moulds for Concrete Cubes

Cast-iron mould specifications, dimensional tolerances.

* Earlier editions were IS 516:1959 and IS 1199:1959 — both superseded by the 2018-part-wise revisions while keeping the same standard number. Confirm the latest published revision on the BIS catalogue before quoting on a project.

Sampling frequency

One sample = a set of 3 specimens, all tested at 28 days; a 7-day result comes from a separate, additional sample. Take samples at the point of placement, not at the plant outlet.

Quantity of concrete (m³)Minimum samples
1 – 51
6 – 152
16 – 303
31 – 504
51 & above4 + 1 per additional 50 m³ or part thereof

Reference: IS 456:2000 Clause 15.2

The procedure, step by step

1

Sampling

IS 1199 (Part 1):2018

  • · Collect concrete at the point of placement using a clean, non-absorbent container.
  • · Take the sample from the middle third of the discharge.
  • · Re-mix with a shovel or trowel to ensure uniformity before moulding.
  • · Slump/temperature record should be noted alongside the sample ID.
2

Casting

150 mm cubes · 3 layers · 35 strokes each

  • · Clean mould, apply release agent, assemble tightly.
  • · Fill in 3 equal layers. Compact each layer with 35 strokes of a 16 mm tamping rod.
  • · Distribute strokes uniformly across the cross-section.
  • · Tap mould sides gently to release trapped air.
  • · Strike off flush with a trowel. Label with sample ID, date, grade, location.
3

Curing

27 ± 2 °C · ≥ 95% RH

  • · Cover moulds to prevent moisture loss; keep at 27 ± 2 °C for the first 24 hours.
  • · Demould at 24 ± 0.5 hours from time of adding water to mix.
  • · Transfer cubes to clean, fresh water tank at 27 ± 2 °C until testing.
  • · Test at 7 days or 28 days. Mark the test age on the cube.
4

Testing

14 MPa/min loading rate

  • · Remove cube from water; surface-dry. Weigh and dimension (150 mm assumed).
  • · Place centrally in the testing machine between platens.
  • · Apply load uniformly at 14 MPa/min (≈ 315 kN/min for a 150 mm cube).
  • · Record max load, compute area, calculate strength (load / area).
  • · Note the failure pattern (see below).

A laboratory system has to carry this step, not just record it: the standard and clause travel with the number, so a result cannot be read out of context. CMDApp's testing laboratory module holds fresh and hardened concrete, cement, aggregate, admixture and durability tests, each carrying the method it was run to.

Assumed σ when you don't have 30 samples

IS 456 Table 8 gives assumed standard deviation values to use when you don't have enough history:

GradeAssumed σ (MPa)
M10 – M153.5
M20 – M254.0
M30 – M555.0
M60 – M806.0

Worked example — M30 grade

fck = 30 MPa, σ assumed = 5.0 MPa.

Group average criterion (Table 11, Cl. 16.1)
  • Option A: fck + 0.825σ = 30 + 0.825 × 5 = 34.125 → 34.0 MPa (rounded to nearest 0.5)
  • Option B: fck + 3 = 30 + 3 = 33 MPa
  • Higher of the two → 34.0 MPa
Individual criterion
  • fck − 3 = 30 − 3 = 27 MPa
  • No single cube (28-day) should drop below this.

Reading the failure pattern

IS 516 specifies a normal conical failure as the qualifying mode. Anything else is a flag for your investigation.

✓ Normal Conical

Both ends intact, double cone forms in the middle. Specified pattern — use the result.

⚠ Columnar

Vertical cracks through cube. Platen restraint issue or capping problem. Retest a spare cube.

⚠ Shear

Diagonal failure along one plane. Possible weak interface or capping weakness. Investigate.

✗ Explosive

Cube shatters violently. Possibly due to impact loading or very brittle mix. Result may not be valid.

Field-checklist blocks

A short questionnaire, an inspector's checklist, and three worked examples that show how the IS 516 sampling-to-failure-pattern logic resolves into a decision on site.

Questionnaire — asked at the point of sampling, before the pour is released

  1. Where is this sample being drawn? At the point of placement, never at the plant outlet, taken from the middle third of the discharge and re-mixed before moulding.
  2. How many specimens make up this sample, and at what age? Three specimens, all at 28 days. A 7-day result comes from a separate, additional sample, not from a second cube out of the same set.
  3. How many samples does this pour's volume require under IS 456 Cl 15.2? 1 to 5 m³ takes 1 sample, 6 to 15 m³ takes 2, 16 to 30 m³ takes 3, 31 to 50 m³ takes 4, and 51 m³ and above takes 4 plus one for each additional 50 m³ or part thereof.
  4. Is the mould clean, release-agented and assembled tightly, and is it a mould to IS 10086?
  5. Has the concrete been compacted in three equal layers with 35 strokes of a 16 mm tamping rod per layer? Strokes distributed uniformly across the cross-section, mould sides tapped to release trapped air, top struck off flush.
  6. Has the mould been kept covered at 27 ± 2 °C, and demoulded at 24 ± 0.5 hours from the time water was added to the mix?
  7. Is the testing machine applying load at 14 MPa/min, which is about 315 kN/min for a 150 mm cube, and has the rate control been checked? A machine without rate control gives you misleading numbers.
  8. What will you do with the result if the cube fails in a pattern other than the normal cone? Normal conical is the qualifying mode. Columnar, shear and explosive each call for a different action, so decide the action before you press the button.

Inspector's checklist — what to verify on site

  1. Sample identity: sample ID, date, grade and location labelled on the cube, with slump and temperature noted alongside the sample ID and the sampling point recorded as the point of placement.
  2. Sample count against pour volume: checked against the IS 456 Cl 15.2 table. A 60 m³ pour takes 5 samples; a 20 m³ pour takes 3.
  3. Mould condition: clean, release agent applied, assembled tightly, no leakage at the joints.
  4. Compaction record: three equal layers, 35 strokes of a 16 mm tamping rod per layer, strokes spread over the cross-section.
  5. Curing record: 27 ± 2 °C and at least 95% RH, demoulded at 24 ± 0.5 hours from the time water was added to the mix, then immersed in clean water at 27 ± 2 °C until the test age.
  6. Test age marked on every cube, and each sample's three specimens all at 28 days.
  7. Machine check before the day's first cube: loading rate 14 MPa/min (about 315 kN/min on a 150 mm cube), cube centred between the platens, surface dried and dimensions and weight taken before loading.
  8. Failure pattern logged against every cube: normal conical (use the result), columnar (retest a spare cube), shear (investigate), explosive (result may not be valid).

What happens if… three worked examples

Example 1 — 60 m³ of M30 arrives as one pour

What happens. IS 456 Cl 15.2 puts 51 m³ and above at 4 samples plus one for each additional 50 m³ or part thereof, so 60 m³ needs 4 + 1 = 5 samples. One sample is three specimens, so 15 cubes at 28 days, all cast from concrete re-mixed and taken at the point of placement.
Likely outcome. Five sample results exist, so the group-of-four rule in IS 456 Table 11 applies and the small-quantity rule does not (the quantity is over 30 m³ in any case). The first four consecutive results form the first group and the fifth starts the next. If you also want a 7-day figure, that is a separate additional sample, not two cubes lifted out of one set.

Example 2 — a 20 m³ M30 pour on a small foundation

What happens. 16 to 30 m³ takes 3 samples under IS 456 Cl 15.2, so 9 cubes at 28 days. Because the quantity is 30 m³ or less and fewer than four samples are available, IS 456 Table 11 Note 2 governs instead of the group-of-four rule: the mean of all three sample results must reach fck + 4 = 30 + 4 = 34 N/mm², and each individual result must reach fck − 2 = 30 − 2 = 28 N/mm².
Likely outcome. The individual floor tightens from 27 N/mm² (fck − 3, the figure that applies to M30 in the group regime) to 28 N/mm², and three results carry the whole pour. If only one sample is taken, that single result has to reach 34 N/mm² on its own. Reaching for the group-of-four arithmetic on a small pour is the easiest mistake to make and the most expensive one to discover late.

Example 3 — the third cube comes out with vertical cracks

What happens. IS 516 makes the normal conical failure the qualifying mode, so a columnar failure is a platen restraint or capping problem, not a strength verdict. Retest the spare cube from the same sample, and check the machine while you wait: load must go on at 14 MPa/min, which for a 150 mm cube is about 315 kN/min, and a machine without rate control gives misleading numbers.
Likely outcome. The spare cube's result stands if it fails conically. If the spare fails columnar as well, the fault is in the testing rather than the concrete, so the result set is quarantined pending a machine check and a repeat test. That quarantine is the honest answer. Filing a doubtful number because the pour is waiting is how a cube test stops being evidence.

Frequently Asked Questions

Related articles

AH
About the author

Amit Haridas

Founder & Proprietor, ConcreteInfo. 25+ years experience in construction QA/QC, concrete technology, and RMC plant operations. NRMCA Certified Trainer (USA) and ISO Lead Auditor.

Indicative tool — not a substitute for engineering judgement. Results are computed from formulae and reference values cited to Indian Standards and other published codes as named on this page, using nominal default assumptions; clause and table references are given in good faith for study and preliminary checks. Always verify the current edition and amendments of any cited standard in the BIS catalogue before relying on it. Final mix proportions, structural checks and construction decisions must be confirmed by a qualified engineer against the project design brief, drawings and site conditions. ConcreteInfo accepts no liability for design, procurement or construction decisions taken on the basis of these tools. Code references & rights: Indian Standards are the property of the Bureau of Indian Standards (© BIS) — official PDFs at bis.gov.in. Shared in good faith as technical reference for the civil engineering fraternity — always verify against the official publication.
Newsletter

Technical updates, not sales emails

One email when a new article goes out on concrete technology, QA/QC and construction quality. No promotions, and your address is never sold or passed to advertising networks. Subscribing is separate from making an enquiry.

You are on the list.

One email when a new article goes out. Every issue carries an unsubscribe link.